Delays expected as motorway work starts

M4 motorway M4 motorway

MOTORISTS using the M4 near Chippenham are being warned to expect delays as safety work will take place for three months.

Improvements costing £5m are to be carried out on the motorway between Junction 16 (West Swindon) and Junction 17 (Chippenham).

The work starts on Monday and continues until May.

During the work only two lanes will be open; the hard shoulder and lane one will be closed. These restrictions will be lifted over Easter.

A 50mph speed limit will be in place during the work and some work will be carried out overnight.

Highways Agency project sponsor Rachel Scott said: “The work has been carefully planned so we can undertake more than one scheme at the same time, which will significantly reduce disruption. However, I advise people to plan their journeys and allow extra time.”

The improvements and maintenance includes the stabilisation of embankments, upgrading traffic signals and the replacement of sections of the steel central reservation barriers with concrete barriers.

The Highways Agency says the new concrete barriers are stronger and more robust. They reduce the risk of vehicles involved in accidents crossing from one side of the motorway to the other and improve the safety of motorists and road workers. Further work taking place during the same time will be drainage repairs and fence replacement.

Work on the M4 between Junctions 14 (Hungerford) and 13 (Newbury) is to be completed by the end of the month.